PEAK MINE PROJECT
GREAT COBAR PROJECT (2025-2028)
Metric PCM was engaged to provide Project Consultancy Services during the execution phase of a Program of Projects for the Great Cobar Project which is the development of a new copper deposit to the north of its existing New Cobar Complex.
The Program included the following Projects:
~5700m of capital development to first ore (by owner)
~630m raisebore shaft
Augmentation of existing primary ventilation circuit including: upgrades to existing surface primary ventilation fan, ventilation doors, secondary ventilation fans
Augmentation to 22kV power supply to the mine including coordination of permitting with service providers (Essential Energy)
22/11kV transformers, switchgear and cable dropper into mine
Surface to underground slick lines and service holes
60m3/hr Batch plant
Underground pump station
Water reticulation systems including: piping, tanks, bores and pumps
Replacement air compressor servicing the New Cobar Complex operation
Peak Gold Mines Cobar, New South Wales
Our Project Services Include:
Our Project Team:
Our Project Team includes a construction manager, project engineers, construction superintendents, project controls engineer, project administration support and specialist input as needed from contracts, commissioning, engineering, drafting personnel.